Flower Mound is a town in the north Dallas-Fort Worth Metroplex, in Denton County (with a small area in Tarrant County), near Lake Grapevine and Lewisville Lake on the SH 121 and FM 2499 corridor. The Town publishes department-specific development fee schedules through Planning Services and Engineering Services, and a dedicated impact-fee surface. The development-side families captured on this page are the Town's zoning and development application fees (Planning Services Fee Schedule, Ordinance No. 13-24, effective April 1, 2024) and its Texas Local Government Code Chapter 395 impact fees: roadway impact fees, water impact fees, and wastewater impact fees, all for plats filed on or after April 20, 2026.

On this page
  1. Fee summary
  2. Zoning and development fees
  3. Impact fees
  4. Coverage notes
  5. Fee authorities
  6. Sources

Fee Summary

Fee Type Status Top-Line Figure Effective Date
Zoning and Development Application Fees Confirmed Zoning change $500 + $25/acre (0-20 ac); PD single-family $2,935 + $25/acre; specific use permit $625 (0-5 ac) / $2,635 (5+ ac); site plan $2,115 + $210/building 2024-04-01
Impact Fees (TLGC Ch. 395 roadway + water + wastewater) Confirmed Roadway per vehicle-mile $682 (A) / $2,697 (B) / $2,949 (C); water 5/8"x3/4" $10,317; wastewater by service-area district, Long Prairie Conservation District $0 2026-04-20
Utility Tap / Connection Fees Not administered separately The development-side water and wastewater connection charge is administered as the impact fee; no separate developer tap or meter-set fee schedule is published -
Cash Proffers Does not apply Cash proffers are a Virginia statutory framework only; Texas jurisdictions do not use them -
Special District Fees (PID / TIRZ / MUD) Not administered by this jurisdiction TIRZ No. 1 and No. 2 are tax-increment financing zones on the tax roll; the Town's fee schedules contain no PID or MUD developer fee entries -

Zoning and Development Application Fees

Source: Town of Flower Mound Planning Services Fee Schedule, effective April 1, 2024 (Ordinance No. 13-24; SHA-256 4beb7d79...). Fees are tiered by acreage where noted. A plan review deposit of $500.00 (nonrefundable) is due at application submittal for zoning amendments, planned developments, specific use permits, and site plans. Legal notification fees also apply: $2.50 per property owner notice mailed and $40 per newspaper legal notice.

Zoning, Planned Development, and Specific Use Permits

Fee ItemAmount
Zoning Change (0 to 20 acres)$500 + $25/acre
Zoning Change (20+ to 50 acres / 50+ acres)$1,270 / $1,310
Zoning Planned Development - Single Family (0 to 20 acres)$2,935 + $25/acre
Zoning Planned Development - Conservation (0 to 20 acres)$4,320 + $25/acre
Zoning PD - Multi-Family and Non-Residential / Mixed Use (0 to 20 acres)$4,005 + $25/acre
Zoning - Minor Amendment (includes minor PD and MU)$1,000
Specific Use Permit (0 to 5 acres / 5+ acres)$625 / $2,635
Master Plan Amendment (0 to 20 acres)$1,355 + $25/acre
Zoning Verification Letter$25
Plan review deposit (Zoning Amendments, PDs, SUPs, Site Plans)$500.00 nonrefundable at submittal

Site Plans, Plats, and Analysis

Fee ItemAmount
Site Plan - All Except Multi-Family$2,115 + $210/additional building
Site Plan - Multi-Family$2,455 + $105/additional building
Record Plat - Single Family Residential (0-50 acres)$300 + $10/acre
Subdivision Site Plan - Single Family Residential (0-50 acres)$1,140 + $10/acre
Replats - All Types (Residential and Non-Residential)$400
Minor Plats (single-family / multi-family and non-residential)$300 / $350
Vacating Plats - All Types$1,960
Transportation Analysis (TA)$2,500
Water Capacity Analysis$550
Wastewater Analysis$550
Legal notification - property owner notice (per notice mailed)$2.50
Legal notification - newspaper legal notice (each)$40

Impact Fees - Roadway, Water, and Wastewater

Source: Town of Flower Mound Roadway Impact Fees, Exhibit F (SHA-256 18544aa7...) and Water and Wastewater Impact Fees, Exhibit E (SHA-256 5a614708...). Under Texas Local Government Code Chapter 395, the Town assesses roadway impact fees per vehicle-mile by ITE land-use category and Service Area, and water and wastewater impact fees by meter size. All three components apply to plats filed on or after April 20, 2026.

Roadway Impact Fees

Fee ItemAmount (Service Area A / B / C)
Roadway impact fee per vehicle-mile$682 / $2,697 / $2,949
Single-Family Detached Housing (ITE 210, per dwelling unit)$3,103.10 / $12,271.35 / $13,417.95
Multifamily Housing (Apartment / Condo, ITE 220, per dwelling unit)$1,739.10 / $6,877.35 / $7,519.95
General Light Industrial (ITE 110, per 1,000 SF GFA)$1,670.90 / $6,607.65 / $7,225.05
Hotel (ITE 310, per room)$1,029.82 / $4,072.47 / $4,452.99

Water Impact Fees (Town Wide Service Area, by meter size)

Meter SizeAmount
5/8" x 3/4" meter$10,317
1" meter$25,793
2" Compound meter$82,536
10" Turbine meter$3,610,950

Wastewater Impact Fees (by service-area district and meter size)

Service-Area District 5/8" x 3/4" 2" PD 10" Turbine
Long Prairie Conservation District$0$0$0
Denton Creek District$5,621$44,968$1,967,350
Cross Timbers Lakeside District$1,064$8,512$372,400
Additional service-area district$1,314$10,512$459,900

The wastewater impact fee schedule divides the Town into four service-area districts. The dollar amounts above are captured verbatim from Exhibit E; the Long Prairie Conservation District is assessed at $0. The name of the fourth service-area district was not legible in the source extraction and is shown here as "Additional service-area district" rather than asserted, consistent with ZoneFee's no-fabrication rule. Confirm the district names and the meter sizes that apply to a specific project directly with the Town.

Coverage Notes - What This Page Does Not Cover

Per ZoneFee's Partial-Verified Publication Standard, the items below were not closed via confirmed fee amounts on this page. They are disclosed here rather than estimated or omitted silently.

Utility Tap / Connection Fees

The Town of Flower Mound's development-side water and wastewater connection and capacity charges are administered as the Water Impact Fees and Wastewater Impact Fees (captured above; assessed by meter size at plat), not as a separate developer tap or meter-set fee schedule. Three official surfaces were probed: the Engineering Services Fee Schedule (design review and inspection fees, landscape and drainage inspection fees, and the Section 90-221 subdivision inspection fee, but no water or sewer tap or meter-set fee), the Utility Services page (water-conservation material only), and the Utility Applications and Forms page (service applications and meter-install forms, not a fee schedule). Closed-search outcome: unavailable via official sources - the development-side charge is the impact fee.

Cash Proffers

Cash proffers are a Virginia statutory framework only (Va. Code 15.2-2303 and 15.2-2303.4); Texas jurisdictions do not use cash proffers. Developer-side contributions in Flower Mound occur through impact fees (the Texas Local Government Code Chapter 395 roadway, water, and wastewater impact fees, captured above) and zoning and development application fees. Closed-search outcome: fee family does not apply.

Special District Fees (PID / TIRZ / MUD)

The Town of Flower Mound maintains two Tax Increment Reinvestment Zones (TIRZ No. 1 and TIRZ No. 2), but a TIRZ is a tax-increment financing mechanism administered through the tax roll, not a developer-facing special-district application or assessment fee. The Planning Services Fee Schedule, Engineering Services Fee Schedule, and the roadway, water, and wastewater impact fee tables contain no PID (Public Improvement District) or MUD (Municipal Utility District) developer fee entries. Closed-search outcome: not administered by this jurisdiction.

Fee Authorities

Authority Fee Types Official Website
Town of Flower Mound (Planning Services / Engineering Services / Building Inspections; impact fees adopted by Town Council) Zoning change and planned development; specific use permits; site plans; plats; master plan amendments; engineering review and inspection; roadway, water, and wastewater impact fees flowermound.gov

Sources

Last verified by ZoneFee: 2026-06-02. Fee schedules are subject to change. Verify current rates directly with the Town of Flower Mound before relying on this data for any financial decision.

This page reflects fee data sourced from the Town of Flower Mound's Roadway Impact Fees (Exhibit F; SHA-256 18544aa7...), Water and Wastewater Impact Fees (Exhibit E; SHA-256 5a614708...), and Planning Services Fee Schedule (Ordinance No. 13-24, effective April 1, 2024; SHA-256 4beb7d79...). ZoneFee does not guarantee that fee amounts are current at the time you read this page. Fee schedules change. The roadway, water, and wastewater impact fees apply to plats filed on or after April 20, 2026, and the amount assessed on a specific project depends on its land-use category, service area, and meter size. The Town's development-side water and wastewater connection charge is administered as the impact fee; Texas jurisdictions do not use cash proffers; and the Town's schedules administer no PID, TIRZ, or MUD developer-facing application fee. Verify all current rates directly with the Town of Flower Mound before relying on this data for land acquisition, project budgeting, or any financial decision. This page is for research and due-diligence reference only - it is not legal or financial advice.